Quay reinforcement at Hamburg Harbour
Front page > Foundation works > References > Quay reinforcement at Hamburg Harbour < Back
Secant pile wall in Odense
Flood protection in Hamburg
Quay reinforcement at Hamburg Harbour

Due to an ever increasing number of large ships calling at Hamburg Harbour it became necessary to deepen the quay berths by three metres in 1999-2000.

In this connection Aarsleff in cooperation with German Ed. Züblin AG was awarded the contract on reinforcement of 200 metres of existing quay.

The reinforcement consisted of a combined wall of tubular piles and sheet piles completed with a concrete cabin beam. From here we implemented a horizontal anchoring ten metres ashore, where the energy was absorbed by a new concrete beam anchored with a land tie.  

The work was carried out under normal activity on the quay and while ships were unloaded and loaded. Therefore, horizontal anchoring was necessary in order to avoid undermining the structural frame for the cranes at the harbour. 


Contact
Chief Estimator
Jens M. Jørgensen
+45 8744 2503
jmj@aarsleff.com
Estimator
Mogens Jensen
+45 3679 3500
mje@aarsleff.com
Related topics
Marine construction


Copyright © 2008 - Terms of use
Per Aarsleff A/S, Lokesvej 15, 8230 Åbyhøj, Tel +45 8744 2222, Fax +45 8744 2249, Mail:info@aarsleff.com / job@aarsleff.com